LC VBL start work on project transportation of OOG equipment for modernization of Omsk refinery PJS «Gazprom Neft» in the framework of the contract with JSC «Infotech-Baltika» during summer navigation of 2016 from June till October.
Main points in HL&OOG delivery project for Omsky Refinery:
• Two parties of HL&OOG cargoes from Saint-Petersburg (6 units by 1 barge) and from Volgograd (9 units by 3 barges) delivered to the Port of Tallinn for consolidation and further transshipment to one geared vessel and transportation to the Ob Bay;
• VBL attracted geared vessel Jumbo Shipping for third party delivery from China to the Ob Bay (transshipment of 8 units on 6 barges);
• Laborious and complex operation of HL&OOG direct transshipment from two geared vessels to barges implemented under management of LC VBL project managers and engineer companies representatives on the road of the port of Sabetta
Plus as part of this project unique transportation Atmospheric column was completed from Volgograd to Omsk (9000 km), on the barge, through the Belomoro-Baltyiyskiy Channel and produced by unloading using RORO method.